Johns Creek has launched a multi-year Neighborhood Repaving initiative. In an effort to keep our residents informed about the project’s progress, we are offering a tentative schedule showing when each neighborhood repaving project is supposed to start.
The schedule is dependent on many variables, including the weather and the availability of extra crews. We will update our schedule weekly, listing neighborhoods to be repaved over the next two weeks. We encourage you to check the schedule frequently as the schedule may change.
Rest assured that we intend to work as fast as possible while maintaining the quality that Johns Creek residents expect. Paving will be done during daylight hours.
Thank you for your understanding and cooperation.
*Please note the schedule is subject to change!
2022 Neighborhood Repaving Schedule
Subdivision |
Patching Start Date |
Milling start Date |
Topping Start Date |
Spring Garden |
|
June 23 |
June 27 |
Lakehill |
|
|
|
Creekside Crossing |
|
|
|
Medlock Bridge |
|
June 24 |
June 27 |
Bridgestone |
|
|
|
Parsons Station |
|
|
|
View the
2022 Neighborhood Repaving Map [PDF]
2022 Main Roads Repaving
Main Road |
Patching Start Date |
Milling Start Date |
Topping Start Date |
McGinnis Ferry (Chattahoochee River to Bell Road) |
July 27 |
N/A |
Aug. 1 |
East Fox Court (Jones Bridge Road to City Limits) |
July 26 |
N/A |
July 26 |
State Bridge Road (Medlock Bridge to River Park Drive) |
July 18 |
July 20 |
July 22 |
Brumbelow Road (Old Alabama Road to Nesbit Ferry Road) |
July 5 |
July 8 |
July 12 |
Abberly Cove (Servicing Morton Road Park) |
July 25 |
N/A |
July 25 |
View the
2022 Main Roads Repaving Map [PDF]