Repaving Schedule

Johns Creek has launched a multi-year Neighborhood Repaving initiative. In an effort to keep our residents informed about the project’s progress, we are offering a tentative schedule showing when each neighborhood repaving project is supposed to start.

The schedule is dependent on many variables, including the weather and the availability of extra crews. We will update our schedule weekly, listing neighborhoods to be repaved over the next two weeks.  We encourage you to check the schedule frequently as the schedule may change.

Rest assured that we intend to work as fast as possible while maintaining the quality that Johns Creek residents expect. Paving will be done during daylight hours.

Thank you for your understanding and cooperation.

Neighborhood Repaving Schedule

Subdivision Patching Start Date Milling Start Date Topping Start Date
Cameron ForestCompleted COMPLETED COMPLETED COMPLETED
Falcon Ridge COMPLETED COMPLETED COMPLETED
Timber Lane COMPLETED COMPLETED COMPLETED
Abbotts Station COMPLETED COMPLETED COMPLETED
Randolph Hall COMPLETED COMPLETED COMPLETED
Devon Hall      
Lexington Woods COMPLETED COMPLETED COMPLETED
Cambridge COMPLETED In Progress Thurs, June 29
Crossington Rd COMPLETED COMPLETED COMPLETED
Fairway Ridge      
North Peak      
Preston Oaks      
Stratmore      
River Farms      
The Gates      
The Falls of Autry Mill      
Oxford Mill      


Main Roads Repaving Schedule

Roads Milling Start Date Patching Start Date Topping Start Date
Rogers Circle COMPLETED COMPLETED Wed, June 28
Findley Road COMPLETED Mon, June 26 Wed, June 28
Morton Road In Progress Tues, June 27 Tues, June 27


*The schedule will be subject to change due to weather and availability of additional crews.